Monaco Hickey was instrumental in delivering a world-class plasma product production facility for the global, biopharmaceutical company, CSL.
Three levels were constructed, incorporating an extensive electrical and mechanical building plant, new substation, transformers, re-production plant infrastructure, production processing, administrative support offices and warehousing.
Monaco Hickey successfully co-ordinated and site managed approximately $100m of product processing equipment and services in conjunction with facility construction.
The finished building features a heavily loaded concrete floor and lightweight, long-span roof-truss framing, which provides a separation of trafficable plant and ceiling spaces from clean spaces underneath. Upon accomplishing completion of the structure, Monaco Hickey was also engaged to integrate specialist tenancy fit-outs
This project delivered a state-of-the-art, clean room manufacturing facility, and was finished on time and within budget. The structure received an MBAV Award in 2014, which recognised the building’s outstanding construction.
CLIENT
ARCHITECT
Monaco Hickey successfully co-ordinated and site managed approximately $100m of product processing equipment and services in conjunction with facility construction.